This page catalogs the status and todo list for our Santa Clara EOC to Layer 42 link build.
(X-completed Nov 17) Layer 42
Andy
- X Pick mount location and height with Dan next week.
Lowell
- X Gather materials
- X Unistrut
- X U brackets
- X Pole
Layer 42 guys
- X Attach unistrut to parapet
SNCEOC
Bill Rainey
- Buy another spool of weatherproof cable.
- Set up premises equipment
- Computer
- Ethernet
- Browser
- Linphone
Andy
- Figure out what kind of cable to get.
- X Get radio configs ready.
- X Send radio config to Bill.
Bill and Andy
- Range test NS5's with add on reflectors